Money Pile: Norfolk Consolidated Court Complex Phase 2

By / Uncategorized / Comments Off on Money Pile: Norfolk Consolidated Court Complex Phase 2

Final Dewaal pile installed at Phase 2 of Norfolk Consolidated Court Complex for Walsh Construction on September 25, 2015. All 241 piles installed in 8 days, which was 4 days sooner than the scheduled 12 days. Morris-Shea pulled off another successful and safe project with very tight site and strict guidelines on noise and vibrations so adjacent court activities were not interrupted. Many thanks to Walsh’s building group out of Pittsburgh for helping to implement this value engineering Dewaal pile alternate for this project.